AMOrtegaLogo_blackwhite-small
Circuit 1090 Trench and Conduit

CLIENT: SAN DIEGO GAS AND ELECTRIC LOCATION: JAMUL, CALIFORNIA

SERVICE: UNDERGROUND INFRASTRUCTURE

Scope: Installation of duct bank for new 12kV underground distribution circuit to serve residential and commercial customers in the unincorporated area of Jamul, CA., including all trenching, installations, backfill, surface repairs and finish paving on State Hwy. 94.

Project Duration: 1 Year

Pipeline Safety Enhancement Plan

CLIENT: Southern California Gas Company LOCATION: Banning, CALIFORNIA

SERVICE: Natural Gas Pipelines

Scope: Scope: Constructed two new main line valve stations with all associated piping and fixtures for Banning airport.

Project Duration: 3 Months

Conduit Installation for Telecommunications

CLIENT: Habitat for humanity
LOCATION: Imperial Beach, CALIFORNIA

SERVICE: Grading, Paving and Fencing

Scope: Installed 2-4” conduit for secondary electric and 2-4” conduit for telecommunications from meter location to pole. Excavation and installation of gas service line from 10th Street Main to meter location. Assisted SDG&E with tie overs and energizing service. Asphalt restoration; Asphalt concrete base and cap in accordance with applicable municipal standards.

Project Duration: 8 Months

Public and Private Utility Upgrades

CLIENT: MHP Utility Upgrade Program – Regal Mobile Estates
LOCATION: Costa Mesa, CALIFORNIA

SERVICE: Joint Facilities

Scope: Installed mains and services in public and private property to Mobile Home Park (MHP) Regal Mobile Estates. Performed all installation and abandonment work, including purging the legacy system. Performed all joint trench, joint paving and to the meter work.

Project Duration: 4 Months

Southbay Substation Relocation

CLIENT: San Diego Gas & Electric
LOCATION: Chula Vista, CALIFORNIA

SERVICE: Underground Infrastructure

Scope: Trenching, conduit and substructure work, including installation of five (5) augured pier foundations for five (5) 69kV steel riser poles and one (1) 138kV augured pier foundation for one (1) 138kV steel riser pole as part of the Southbay Relocation project located near Bay Blvd. in Chula Vista, California.

Project Duration: 10 Months

Industry Awards and Recognition

2019 LEADERSHIP RECOGNITION AWARD

Local Union 345

2018 GENE PAINE AWARD FOR OUTSTANDING LEADERSHIP

Ducks Unlimited California

2013 MBE SUPPLIER OF THE YEAR, CLASS III

San Diego Regional Minority Supplier Development Council

2012 – 2013 DBE SUPPLIER OF THE YEAR

Sempra Energy Utility

2011 – 2012 DBE SUPPLIER OF THE YEAR

Sempra Energy Utility

2011 SMALL BUSINESS OF THE YEAR

SDG&E – Sempra Energy Utility

2009 – 2010 BEST OF LAKESIDE AWARD

United States Commerce Association

Let’s get started

Since 1974, our core values have been safety and quality workmanship – these will continue to be our watchwords as we move forward with the next generation of workers and leadership. As infrastructure components begin to reach the end of their useful life in the next few years, our industry will continue to increase in importance and workload as we have always done.